Friday Nov 22, 2024
Friday Nov 22, 2024

Dordikhola Hydropower Project begins power generation


Nepalnews
RSS
2022 Aug 29, 7:41, Lamjung
Representative Image Photo: Google

The Dordikhola Hydropower Project in the Lamjung district has begun test production on Sunday.

The project with a capacity of 27 megawatts commenced test production after completing the entire construction works, Project Chief Munna Shakya said.

According to Shakya, the test production will continue for four to five days adding that commercial production of the power will begin once the test production was successful.

The powerhouse of the project is located at Ramchowkbensi of Bensisahar Municipality-11.

The project which was starting to build in 2016 was estimated to generate power in two and a half years but got delayed due to India's economic blockade on Nepal, a flood in the powerhouse in the Marsyangdi river last year, lockdown imposed during the coronavirus period and several other technical issues.

The total cost of the project is estimated to be around Rs 4.64 billion though it was expected to complete with an investment of Rs 4.23 billion.

Non-Resident Nepalis Association (NRNA) has invested 35.7 percent, IME Group has 34.3 percent, and 30 percent of the public for the project development.

Dordikhola Hydropower Project Lamjung megawatts construction works Powerhouse Marsyangdi investment NRNA
Nepal's First Online News Portal
Published by Nepalnews Pvt Ltd
Editor: Raju Silwal
Information Department Registration No. 1505 / 076-77

Contact

Kathmandu, Nepal,


Newsroom
##

E-mail
[email protected]

Terms of Use Disclaimer
© NepalNews. 2021 All rights reserved. | Nepal's First News Portal